Dubník-Svodín, reconstruction of long-distance water pipeline DN 600

Object: SO 01 Reconstruction of long-distance water pipeline km 0.000 00 – 1.359 34 Client: Západoslovenská vodárenská spoločnosť, a.s. Construction period: May 2024 – November 2024 Description of objects: The DN 600 water pipeline in the section Kolta – Svodín is part of the pipeline that supplies the city of Štúrovo and the adjacent villages…

Lipovec – Turčianske Kľačany sewage system – part of Lipovec

Investor Lipovec municipality Contractor: JV TUCON-Combin_Lipovec Construction period: October 2023 – November 2024 Description of objects: Construction of part of the sewage network and sewage connections in the village of Lipovec, specifically on the following SO or PS:   Sewer network Lipovec SO 19 – Lipovec sewage network SO 19/A – Lipovec sewage network -…

Sewerage of the municipality of Pribeta and WWTP Pribeta

https://www.martias.sk/wp-content/uploads/MARTI-Pribeta-FullHD.mp4 Investor Municipality of Pribeta Construction period June 2023 – January 2025 Description of objects: The subject of the filling is the gravity sewer PVC DN 250 and DN300 of 20 716m length, the HDPE sewage printout DN 65 and DN 80 of 2 043m length, including 8x CHS and 1 218x (9 402m) PVC…

VDJ Vtáčnik, rehabilitation of the storage chamber

Investor Bratislavská vodárenská spoločnosť, a. s. Construction period July 2023 – April 2024 Description of objects: The subject of the contract is the rehabilitation of the storage chamber at the Reservoir Vtáčnik 1×7300 m3 in Bratislava. The subject of the implementation will be the rehabilitation of walls, ceiling beams, rehabilitation of defects in the structure,…

Sewerage of the group of municipalities of Horný Žitný ostrov stage 5 – Sewerage of Čakany

Investor The village of Čakany Construction period June 2023 – December 2023 Description of objects: The subject of the order is construction work – sewerage of the village of Čakany, based on the project documentation. The construction of the work (stage 5) consists of a sewage network in the territory of the intra-village of the…

Nesvady – expansion of sewerage and WWTP

https://www.martias.sk/wp-content/uploads/MARTI-Nesvady-FullHD.mp4 Investor Západoslovenská vodárenská spoločnosť, a.s. Nábrežie za hydrocentrálou 4, 949 01 Nitra Construction period June 2023 – August 2024 Description of objects: The subject of the contract is the construction of the Work – the expansion of the sewage system and the existing Nesvady WWTP – in the following scope:   construction of a…

Záhorská Bystrica, Renovation of the water supply on Donská street and Reduction shaft, connection near D2

Client Bratislavská vodárenská spoločnost, a.s. Construction period October 2022 – May 2023 Construction technology: The subject of the performance is the implementation of construction works for the rehabilitation of the existing DN200 pipeline for a new pipe made of ductile iron TVLT (PN10) – DN300 with a length of approx. 795 m. The entire rehabilitation…

Bratislava, Hradská street – Reconstruction of the water supply

Client Bratislavská vodárenská spoločnost, a.s. Construction period May 2022 – September 2022 Description of objects: The subject of the performance is the realization of the public water supply pipe on Hradská street, that includes to provide the necessary permits and engineering activity necessary for the realization of the construction. The existing water supply pipe will…

WWTP Kolárovo – reconstruction and extension 1st stage

https://www.tucon.sk/wp-content/uploads/Tucon-Kola-rovo-FHD.mp4 Client: Západoslovenská vodárenská spoločnosť, a.s. Construction period: March 2022 – October 2023 Construction technology: The subject of the project is the reconstruction and extension of the existing Kolárovo WWTP to a total capacity of 13,750 PE. The construction of the WWTP will take place during full operation of the original pumping station resp. without…

Complete reconstruction of the state road N08 Interlaken-Ost-Brienz, Switzerland

Investor Bundesamt für Strassen ASTRA, Filiale Thun, CH-6300 Thun Higher supplier ARGE Marti Brienzersee Construction period January 2021 – December 2022 Description of main objects: Complete reconstruction of the state N08 between Interlaken Ost and Brienz. Section length: 13,83 km maintenance section no. 60 Number of bridges and other civil engineering structures: 38 Number of…