Extension of the sewerage, relocation of the water main, Budatín – Horná street

Client Severoslovenské vodárne a kanalizácie, a.s. Construction period July 2020 – November 2020 Description of the objects: BO 01 Extension of the sewerage Branch B: sewerage system –  PVC SN8 DN300 in the total length of 295,7 m Branch C: sewerage system –  PVC SN8 DN300 in the total length of 129,1 m BO 02 Relocation…

Motorway D1 Prešov West – Prešov South, Fire-protection water main in Tunnel

Client National Motorway Company a.s. General contractor Doprastav a.s. Construction period July 2020 – September 2021 Description of the objects:  Ensuring a sufficient capacity of fire-protection water in case of a fire in the tunnel Technology of construction: Water supply is designed from spigot pipes and ductile iron pipes DN 150 PN 16, system BLUTOP by…

Increasing the security of the area against the backwater of the Little Danube and the Klátovský arm from river Váh, 1st stage

General contractor JV TuCon – VÁHOSTAV SK, Klátovské rameno, Leader of JV – TuCon Construction period October 2019 – April 2022 Technology of the construction: The structure is a flood protection work, which dams the flow of the Klátovský arm and deflects it to the new built river basin. The dam consists of reinforced concrete „Closing…

Dvory nad Žitavou – Sewerage and WWTP

Investor Municipality of Dvory nad Žitavou Construction period July 2019 – August 2020 Technology of the construction: Construction of the village gravity sewerage made of corrugated pipes PVC-U SN8 DN300 and DN 400. New constructed pumping stations will supply pumping of the sewage water from the lowest level with HDPE SDR17 PN10 d90 (110, 160) pressure…