Client
Municipality of Chorvátsky Grob
Construction period
December 2008 – September 2010
Construction technology:
Realisation of water pipeline in open cut area
Executed works:
- installation of water pipeline TVLT DN 400 of 2082 m length in open cut area
- 2x overpressure under the local road DN 600
- cross-over of the local river by the bridge
- execution of 2 monolithic shafts and their equipping in places of connection to existing branch of water distribution DN 400, TVLT