Investor:
Municipality Veľké Zálužie
Main contractor:
JV„Združenie Veľké Zálužie, M-E“
(Members: Marti a.s. a EKO SVIP s.r.o.)
Construction period:
08/2026 – 11/2026
Description:
The project involves the construction of a new sanitary sewerage system with a total length of 13,481 metres, including the installation of 812 sewer connections (809 DN150 connections, 2 DN200 combined connections and 1 DN200 connection). The project includes the comprehensive expansion and upgrading of the wastewater treatment plant (WWTP) to increase its capacity to 4,200 PE (population equivalent). The upgrade will involve the refurbishment and extension of the mechanical pre-treatment facilities, biological treatment stage, tertiary treatment processes, and sludge management system, including all associated infrastructure.