Client
Association of municipalities Agglomeration Hronovce
General contractor
Vodohospodárske stavby, a.s.
Construction period
July 2016 – May 2018
Technology of construction:
Part of sewerage is realized like gravity PVC DN 300 mm and part like discharge pipes HDPE DN 150 mm and DN 80 mm. Works are realized in open excavated trench with vertical walls except of crossing with the road No. I/76 (trenchless technology with steel pipes extruding).
Realized works:
- Object SO-03 Sewerage of Pohronský Ruskov
- Object SO-05 Sewerage of Hronovce