Client
Sewerage and WWTP Čierny Balog
General contractor
BRAVUR, a.s.
Construction period
July 2016 – April 2019
Technology of construction: Open excavation and trenchless construction technology.
Realized works:
- Construction of gravity sewerage DN 300 mm, length 11900 m
- Gravity sewer connections DN 150 mm, length 2300 m
- Pressure sewer connections, length 198 m
- House pumping stations 32 pcs
- Pumping stations ČS1, ČS2, ČS3, ČS4 – building part
- Discharge pipes HDPE, length 368 m