Nesvady – expansion of sewerage and WWTP

Investor

Západoslovenská vodárenská spoločnosť, a.s.
Nábrežie za hydrocentrálou 4, 949 01 Nitra

Construction period

June 2023 – August 2024

Description of objects:

The subject of the contract is the construction of the Work – the expansion of the sewage system and the existing Nesvady WWTP – in the following scope:

 

  • construction of a gravity sewer system with a total length of 21,793.02 m from smooth, full-wall PVC SN8 sewer pipes as follows:

DN300 in length 21,451.59 m

DN400 in length 341.43 m

Revision shafts DN1000 in the number of 571 pcs.,

  • construction of 5 pumping stations (ČS6, ČS7, ČS9, ČS10 and ČS11),
  • construction of 985.10 m HDPE discharge pipes DN80 and DN100 PN10,
  • implementation of 1,378 pieces of DN150 and DN200 SN8 PVC sewer branches with a total length of 9,021.82 m, terminated by a DN400 inspection shaft,
  • expansion of the existing Nesvady WWTP for a projected capacity of 7500 EO.

 

The work contains the following SO and PS:

Sewerage

  • SO 101 Sewer network
  • SO 102 Sewer branches
  • SO 103 pumping stations
  • SO 103.1 pumping stations
  • SO 103.2 LV connections
  • PS 103.1 Machine technology part of PS
  • PS 103.2 ASRTP

 

Waste water treatment plant

  • SO-01 Object of mechanical pre-cleaning
  • SO-02 Entrance pumping station
  • SO-03 Denitrification tanks
  • SO-04 Biological reactors
  • SO-05 Pumping station for treated wastewater
  • SO-06 Sediment trap
  • SO-07 Measuring shaft
  • SO-09 Sediment drainage facility and sediment pumps
  • SO-10 Operating building – reconstruction
  • SO-11 Transshipment of drinking water
  • SO-12 Well and service water distribution
  • SO-13 Connecting pipes
  • SO-14 Preparation of territory and demolition
  • SO-15 Secondary LV cable distributions
  • SO-16 Outdoor lighting
  • SO-17 Communications and paved surfaces
  • SO-18 Terrain and orchard improvements
  • PS-01 Mechanical pre-cleaning and input PS
  • PS-02 Biological cleaning and compressed air distribution
  • PS-03 PS for treated wastewater
  • PS-04 Sediment management
  • PS-05 Electrical installation and MaR