Client
Bratislavská vodárenská spoločnosť, a.s., Bratislava
Construction period
December 2003 – March 2005
Construction technology:
- SO 01 reconstruction of AP sewer building part (from profile 1800/200 to 1400/1700) total length 830.98 m + reconstruction of building shafts
- SO 03 complete replacement of existing sewage system DN 300 and DN 400 in total length of 219 m by classical excavated technology