Investor:
Bratislavská vodárenská spoločnosť, a. s.
Main contractor:
Marti a.s.
Construction period:
10/2025 – 11/2026
Object Description:
The project is an underground linear structure and its subject is the reconstruction of the existing public water main supply DN80 – DN150 with a total length of 814.01 m. The proposed reconstruction works consist of no 1 water main supply branch 1 and no 5 connection branches P1 – P5.
The works will begin with the connection to the existing public water supply LT DN80. The route will cross the regional road No. III/1085 – trenchless, by laying the water supply pipe into a steel main protection. The proposed connection branches P1 – P5 will be gradually connected to the water supply branch 1. The works will be completed by connecting water supply branch 1 to the existing PVC DN100 water supply. A total of 9 underground hydrants and 9 plugs will be installed on the pipe along the route, including no 55 local water supply connections. The water supply reconstruction works will be carried out in the alignment of the original water supply main or next to its original route.
Construction Technology:
The construction works consists of one water supply line 1 and five water main connections P1 – P5:
Main branch 1 – total length 773.50 m:
TVLT DN100 – length 137.60 m
TVLT DN150 – length 635.90 m
Connections P1 – P5 – Total length 40.51 m:
· connection P1 – TVLT DN100 – length 8.69 m
· connection P2 – HDPE D160x9.5 – length 4.97 m
· connection P3 – TVLT DN100 – length 10.99 m
· connection P4 – TVLT DN100 – length 7.04 m
· connection P5 – TVLT DN100 – length 8.82 m
Required pressure tests will be carried out prior to the new watermain commissioning.