Client
Ředitelství silnic a dálnic s. p. [Roads and Motorways Directorate, state-owned enterprise]
Main contractor:
EUROVIA CZ a.s.; MI Roads a.s.; Metrostav TBR a.s.;
Construction period
April 2026 – September 2030
Objects description:
The D11 Motorway is part of the European transport corridor Paris–Nuremberg–Plzeň–Prague–Hradec Králové–Wrocław–Warsaw–Brest–Moscow within the framework of the TEN-T (Trans-European Transport Network) agreement, linking Western and Eastern Europe.
The D11 Motorway, Section 1108 Jaroměř–Trutnov, is a four-lane motorway with a total length of 19.63 km and a design category of D26.0/130. The project includes 24 bridges, 1 wildlife overpass (ecoduct), 1 underpass, 2 grade-separated interchanges, 17 noise barriers, and 1 tunnel. The Kamenný vrch Tunnel is a twin-tube motorway tunnel with physically separated carriageways, approximately 767 m in length.
Technical Parameters of the Kamenný vrch Tunnel
– Left Tunnel Tube (LTT), mined section: 684.0 m
– LTT, cut-and-cover section: Jaroměř portal 36.0 m, Trutnov portal 60.0 m
– Right Tunnel Tube (RTT), mined section: 684.0 m
– RTT, cut-and-cover section: Jaroměř portal 12.0 m, Trutnov portal 60.0 m
– Number of cross-passages: 2
– Theoretical excavation area: approx. 87.3 m²
– Clear cross-sectional area of the tunnel tube: approx. 60.5 m²
Construction technology:
– Combined:
- Mined tunnel sections and tunnel interconnections excavated using conventional cyclic excavation follows the principles of the New Austrian Tunnelling Method (NATM).
- Excavated portal sections using the Cut & Cover (C&C) method
The scope of work to be performed by Marti a.s. will comprise the execution of approximately 50% of the following works: : tunnel excavation, primary and secondary lining works, waterproofing, tunnel drainage, fire water mains, internal tunnel structures, pavements and cable conduits, and tunnel technology.




