Investor:
Severoslovenské vodarne a kanalizácie a.s.
Construction period:
August 2024 – November 2025
Description of objects:
Expansion of the sewage system – implementation of gravity sewerage from PVC pipe DN 315, house connections from PVC DN 160 and manholes DN 400.
Sewer BD … length 1157 m
Sewer BD-1 … length 246 m
Drain D3 … length 167 m
Sewer D3-1 … length 578 m
Drain D3-2 … length 408 m
Construction technology:
excavation work – trench excavation, trench lining, bed under the pipeline, laying of PVC pipe DN 315 (main route) and PVC pipe DN 160 (connections), pipe backfilling, trench backfilling with gradual compaction, installation of concrete inspection manholes DN 1000 and connection inspection manholes PVC DN 400, final treatment of communications